FAQ

The lead time of mass order for gravity die casting must be more than 40 days

2022-06-17

The lead time of mass order for gravity die casting is more than 40 days.

a. Casting process: 80pcs to 120pcs per 12 hours

b. Cutting riser bar and sprue bar, the polishing cutting surface - 5 - 10 days.

c. If there are defect on casting, we need to weld them and polish them again. - 3 - 6 days.

d. Heat treatment 2-4 days

e. Machining 7-15 days


When we got your orders, we are busying on other POs, so we need more than 10 days to arrange your casting. 

We use cookies to offer you a better browsing experience, analyze site traffic and personalize content. By using this site, you agree to our use of cookies. Privacy Policy
Reject Accept